Payment Schedule

On signature of building contract a Deposit of 20% of agreed contract price i.e. unit price plus cost of agreed additional works
Upon completion of foundations 10%
Upon completion to wall height 10%
Upon completion of roof 20%
House "lockable" i.e. windows and doors installed 20%
Completed 15%
Handover and occupation (maximum one month after occupation) 5%  Final payment